Scope of works

Complete M&E consultancy for the affordable housing development.

Affordable housing is engineering at volume, and the economics are unforgiving: a detail that merely inconveniences one house becomes a warranty programme across 561 of them. The value of the consultant is in resolving the repeated unit completely — cold water storage and boosting, the sanitary stack, the metering position, the distribution board and earthing — and then holding that standard through every block.

Alongside the units sits the site-wide work that no buyer ever sees: LV reticulation, substation positions, street lighting and the utility applications whose lead times, not the construction, usually decide when keys can be handed over.

Technical particulars

Units
561 units

What this kind of commission involves

Residential and township work is engineering at volume. A detail that is merely inconvenient on one house becomes a warranty programme across six hundred. The value is in getting the repeated unit exactly right, then holding that standard across every phase — and in the site-wide infrastructure that has to serve phases which will not be built for another five years.

Disciplines engaged

  • Repeated unit services design — the detail that gets built hundreds of times
  • Cold water storage, boosting and internal distribution
  • Sanitary plumbing, soil, waste, vent and below-ground drainage
  • Electrical supply, metering position, distribution boards and earthing
  • Site-wide HV and LV reticulation, substations and feeder pillars
  • Street lighting design, lighting levels and control
  • Fire protection for high-rise and community buildings
  • Community facilities — surau, clubhouse, management office services
  • Telecommunications and ICT provision to each unit
  • Authority submissions, utility applications and phase-by-phase certification

What we watch for

The failures that recur on this building type, and where we look for them.

  • A repeated detail approved without a mock-up, then multiplied by six hundred
  • Infrastructure sized for the current phase only, stranding later phases
  • Utility application lead times not reflected in the sales launch programme
  • Below-ground drainage clashing with ground beams because it was never modelled